2018-19 Build Site - 507 North Carico, Carbondale, Illinois

We will be working Saturday, January 12th at 507 N. Carico in Carbondale, IL from 8AM until Noon.

We are closing in on the finish line for Jaylen and Jasmine's house. I, personally, have been gone a lot but work has been progressing at 507 N Carico. Doors are painted, trim is done, caulking is done.

We will be cleaning out as much as we can this Saturday, January 12th. Our carpet guy and the plumbers are coming early next week to do their things. Countertop snafu is fixed and we moved the appliances over so we will be installing those this weekend. There are many details to take care of before we dedicate the home and turn over the keys on Saturday, February 2nd.

DEDICATION DATE - Saturday, February 2nd